[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134954":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134954,796,2,"多选题","技术交底的主要内容中第二级交底内容包括（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分部分项工程施工方案",true,{"key":16,"text":17,"correct":18},"B","季节性施工措施",false,{"key":20,"text":21,"correct":14},"C","危险性较大的分部分项施工方案",{"key":23,"text":24,"correct":18},"D","分部、分项工程的概算编制",{"key":26,"text":27,"correct":14},"E","重大危险源的应急救援措施","ACE","2020版教材P310\u002F2019版教材P305 （二）技术交底的主要内容。第一级交底内容为实施性施工组织设计、技术策划、总体施工方案、重大施工方案及超过一定规模的危险性较大的分部分项工程施工方案等。第二级交底主要内容为分部分项工程施工方案、危险性较大的分部分项施工方案等。第三级交底主要内容为分部分项工程的施工工序等。D选项是二级交底里面的危险性较大的分部分项施工方案。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]