[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134948":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134948,796,2,"多选题","路面各结构层线性流水施工时，影响路面流水工期的因素有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","各结构层的持续时间",true,{"key":16,"text":17,"correct":14},"B","搭接类型",{"key":19,"text":20,"correct":14},"C","搭接时距",{"key":22,"text":23,"correct":24},"D","采用的计算方法",false,{"key":26,"text":27,"correct":14},"E","每个影响施工段的因素","ABCE","2020版教材P301\u002F2019版教材P295 一般路面各结构层施工的速度不同，从而持续时间往往不相同。组织路面流水施工时，应注意的要点是：1、各结构层的施工速度和持续时间；2、相邻结构层之间的速度决定了相邻结构层之间的搭接类型；3、相邻结构层工序之间的搭接时距的计算",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]