[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134947":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134947,796,2,"多选题","在对进度计划进行施工准备的可靠性审查时，应重点审查（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工总工期的安排应符合合同工期",false,{"key":16,"text":17,"correct":18},"B","主要骨干人员及施工队伍的进场日期已经落实",true,{"key":20,"text":21,"correct":14},"C","各项施工方案和施工方法应与施工经验和技术水平相适应",{"key":23,"text":24,"correct":14},"D","对动员、清场、假日及天气影响的时间，应有充分的考虑并留有余地",{"key":26,"text":27,"correct":18},"E","所需主要材料和设备的运送日期已有保证","BE","2020版教材P304\u002F2019版教材P298 施工准备的可靠性（1）所需主要材料和设备的运送日期已有保证。（2）主要骨干人员及施工队伍的进场日期已经落实。（3）施工测量、材料检查及标准试验的工作已经安排。（4）驻地建设、进场道路及供电、供水等已经解决或已有可靠的解决方案。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]