[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134945":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134945,796,2,"多选题","某一非关键工作（工序）的持续时间为5d;它的总时差为4d、自由时差为2d，在进度检查时发现拖延了7d。以下论述正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该工程的工期将拖延2d",false,{"key":16,"text":17,"correct":18},"B","该工程的工期将拖延3d",true,{"key":20,"text":21,"correct":14},"C","该工序已经转变为关键工序，而且关键线路至少增加一条",{"key":23,"text":24,"correct":18},"D","如果该工序拖延2d对后续工序无影响，对总工期也无影响",{"key":26,"text":27,"correct":14},"E","由于上述拖延是发生在非关键工作中，即使是业主原因，也不批准工期延长的申请","BD","2020版教材P306\u002F2019版教材P300 该工作为非关键工序，工程的总时差为4天，那么该工序允许的最大延长时间为4天，检查发现拖延了7天，该工程延时间为7-4＝3，超过了总工期则该工序转变为关键工序；如果该工序拖延2天，小于总时间4天，则不影响总工期。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]