[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134942":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134942,796,2,"多选题","对于桥墩采用流水施工时应注意流水施工的相关时间参数有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工过程数",false,{"key":16,"text":17,"correct":14},"B","施工段数",{"key":19,"text":20,"correct":21},"C","流水节拍",true,{"key":23,"text":24,"correct":21},"D","流水步距",{"key":26,"text":27,"correct":21},"E","技术间歇","CDE","2020版教材P290\u002F2019版教材P285 桥梁下部的桥墩施工时，如果设备或者模板数量有限可采用流水施工方式组织施工。对于采用流水施工时应注意流水施工的相关时间参数：流水节拍、流水步距、技术间歇等。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]