[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134941":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134941,796,2,"多选题","施工组织设计完成后，通过对“S”曲线的形状分析，可以（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","定性分析施工组织设计中工作内容安排的合理性",true,{"key":16,"text":17,"correct":14},"B","可利用“香蕉”曲线对进度进行合理安排",{"key":19,"text":20,"correct":14},"C","结合“香蕉”曲线进行施工中的进度控制",{"key":22,"text":23,"correct":14},"D","结合“香蕉”曲线进行施工中的费用控制",{"key":25,"text":26,"correct":27},"E","结合“香蕉”曲线进行施工中的合同控制",false,"ABCD","2020版教材P293\u002F2019版教材P287 施工组织设计完成后，通过对“S”曲线的形状分析，可以定性分析施工组织设计中工作内容安排的合理性，并可利用“香蕉”曲线对进度进行合理安排。同时，“S”曲线还可以在工程项目实施的过程中，结合“香蕉”曲线（工程进度管理曲线）进行施工中的进度、费用控制。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]