[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134928":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134928,796,2,"多选题","成本控制的方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","以目标成本控制成本支出",true,{"key":16,"text":17,"correct":18},"B","以成本计划编制控制成本支出",false,{"key":20,"text":21,"correct":14},"C","以施工方案控制资源消耗",{"key":23,"text":24,"correct":14},"D","用净值法进行工期成本的同步控制",{"key":26,"text":27,"correct":14},"E","运用目标管理控制工程成本","ACDE","本题考查的是公路项目施工成本目标的控制。成本控制的方法有：以目标成本控制成本支出、以施工方案控制资源消耗、用净值法进行工期成本的同步控制、运用目标管理控制工程成本。参见教材P375～376。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]