[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134921":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134921,796,2,"多选题","施工总体部署的内容有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工进度计划",false,{"key":16,"text":17,"correct":18},"B","项目组织机构设置",true,{"key":20,"text":21,"correct":18},"C","施工任务划分",{"key":23,"text":24,"correct":18},"D","拟定主要项目的施工方案",{"key":26,"text":27,"correct":18},"E","主要施工阶段工期分析","BCDE","本题考查的是公路工程施工部署。施工总体部署主要内容包括：项目组织机构设置；施工任务划分；施工顺序；拟定主要项目的施工方案；主要施工阶段工期分析。参见教材P289。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]