[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134914":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134914,796,2,"多选题","进度计划检查的方法常采用（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","横道图比较法",true,{"key":16,"text":17,"correct":14},"B","公路工程进度表",{"key":19,"text":20,"correct":14},"C","“S”曲线比较法",{"key":22,"text":23,"correct":14},"D","前锋线比较法",{"key":25,"text":26,"correct":27},"E","垂直图比较法",false,"ABCD","本题考查的是公路工程进度控制管理。进度计划检查的方法有：横道图比较法、“S”形曲线比较法、“香蕉”形曲线比较法、公路工程进度表、前锋线比较法、一般网络图进度检查的割线法。参见教材P298~299。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]