[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134902":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134902,796,2,"多选题","下列属于地下连续墙施工主要工序的是（）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","挖槽",true,{"key":16,"text":17,"correct":14},"B","下放钢筋笼",{"key":19,"text":20,"correct":14},"C","浇筑混凝土",{"key":22,"text":23,"correct":14},"D","槽段间的连接",{"key":25,"text":26,"correct":27},"E","打入钢护筒",false,"ABCD","地下连续墙施工一般包括挖槽、下放钢筋笼、浇筑混凝土和槽段间的连接四个主要工序。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]