[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134886":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134886,796,2,"多选题","斜拉桥混凝土主梁零号段及其两旁的梁段，在支架和塔下托架上浇筑时，应消除的对变形和施工质量的不良影响因素有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","湿度",false,{"key":16,"text":17,"correct":18},"B","温度",true,{"key":20,"text":21,"correct":14},"C","风力",{"key":23,"text":24,"correct":18},"D","弹性和非弹性变形",{"key":26,"text":27,"correct":18},"E","支承","BDE","本题考查的是斜拉桥施工。主梁零号段及其两旁的梁段，在支架和塔下托架上浇筑时，应消除温度、弹性和非弹性变形及支承等因素对变形和施工质量的不良影响。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]