[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134883,796,2,"多选题","顶推施工主要临时设施及机具设备有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","起重机",true,{"key":16,"text":17,"correct":14},"B","导梁",{"key":19,"text":20,"correct":21},"C","牵引索",false,{"key":23,"text":24,"correct":14},"D","千斤顶",{"key":26,"text":27,"correct":14},"E","滑动装置","ABDE","顶推施工主要临时设施及机具设备有索塔、起重机、导梁、千斤顶、滑动装置、导向纠偏装置。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]