[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134844":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134844,796,2,"多选题","加筋土挡土墙施工工序中，需交叉进行的工序有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","地基处理",false,{"key":16,"text":17,"correct":18},"B","墙面板安装",true,{"key":20,"text":21,"correct":14},"C","墙顶封闭",{"key":23,"text":24,"correct":18},"D","筋带铺设",{"key":26,"text":27,"correct":18},"E","填料填筑与压实","BDE","本题考查的是常用路基挡土墙工程施工技术。加筋土挡土墙施工简便、快速，并且节省劳力和缩短工期，一般包括下列工序：基槽（坑）开挖、地基处理、排水设施、基础浇（砌）筑、构件预制与安装、筋带铺设、填料填筑与压实、墙顶封闭等，其中现场墙面板拼装、筋带铺设、填料填筑与压实等工序是交叉进行的。参见教材P35。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]