[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134816":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134816,796,2,"多选题","在雨期进行道路路堑开挖，正确的开挖措施有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","土质路堑开挖前，在路堑边坡坡顶2m以外开挖截水沟并接通出水口",true,{"key":16,"text":17,"correct":14},"B","开挖土质路堑宜分层开挖，每挖一层均应设置排水纵横坡",{"key":19,"text":20,"correct":21},"C","挖方边坡一次挖到设计标高，防止沉降",false,{"key":23,"text":24,"correct":14},"D","土的强度低于规定值时应按设计要求进行处理",{"key":26,"text":27,"correct":21},"E","雨期开挖岩石路堑，炮眼应倾斜45°设置","ABD","本题考查的是路基雨期施工技术。开挖土质路堑宜分层开挖，每挖一层均应设置排水纵横坡。挖方边坡不宜一次挖到设计标高，应沿坡面留30cm厚，待雨期过后整修到设计坡度。以挖作填的挖方应随挖随运随填。雨期开挖岩石路堑，炮眼应尽量水平设置。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]