[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134809":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134809,796,2,"多选题","推土机填筑路堤作业时，影响作业效率的是（）环节。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","切土",true,{"key":16,"text":17,"correct":14},"B","运土",{"key":19,"text":20,"correct":21},"C","堆卸",false,{"key":23,"text":24,"correct":21},"D","空返",{"key":26,"text":27,"correct":21},"E","倒退","AB","本题考查的是土质路堤施工技术。推土机作业方式通常是由切土、推土、卸土、倒退、空回等环节组成。而影响作业效率的主要是切土和运土两个环节。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]