[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134796":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134796,796,2,"多选题","下列选项对于隧道开挖的要求，说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","按设计要求开挖出断面",true,{"key":16,"text":17,"correct":18},"B","掘进速度慢，少占作业循环时间",false,{"key":20,"text":21,"correct":18},"C","石渣块度（石渣大小）越大越好",{"key":23,"text":24,"correct":14},"D","应严格控制欠挖，尽量减少超挖",{"key":26,"text":27,"correct":14},"E","尽量节省爆破器材消耗","ADE","本题考查的是公路隧道主要开挖方式、适用范围、开挖要求及超欠挖控制。选项B：掘进速度快，少占作业循环时间；选项C：石渣块度（石渣大小）便于装渣作业。参见教材P230。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]