[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134792":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134792,796,2,"多选题","在流沙段开挖隧道，可采用的治理措施有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","必要时采取井点法降低地下水位",true,{"key":16,"text":17,"correct":14},"B","采用注浆法充填裂隙",{"key":19,"text":20,"correct":21},"C","采用从下而上分步开挖",false,{"key":23,"text":24,"correct":14},"D","建立地表沟槽导排系统",{"key":26,"text":27,"correct":14},"E","流沙地段隧道宜采用超短台阶、环形开挖预留核心土法人工开挖","ABDE","本题考查的是流沙地段施工特点。隧道通过流沙地段，处理地下水的问题，是解决隧道流沙、流泥施工难题中的首要关键技术。施工时，因地制宜，采用“防、截、排、堵”的治理方法。选项C，开挖时必须采取自上而下分步进行。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]