[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134784":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1134784,796,2,"多选题","复合式衬砌隧道的必测项目有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","围岩体内位移",false,{"key":16,"text":17,"correct":18},"B","地表下沉",true,{"key":20,"text":21,"correct":18},"C","净空变化",{"key":23,"text":24,"correct":18},"D","拱顶下沉",{"key":26,"text":27,"correct":14},"E","锚杆轴力及抗拔力","BCD","本题考查的是隧道施工监控量测技术。必测项目有4项：洞内外观察、净空变化、拱顶下沉、地表下沉。",{"id":6,"name":31,"category":32,"favorite":33},"一建公路工程实务","建筑工程",0]