[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134742,796,1,"单选题","悬索桥主缆施工的主要工序包括：①主缆架设；②猫道架设；③索夹安装与吊索架设；④紧缆；⑤牵引系统施工。其正确的施工工序为（ ）。2013年",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④→⑤",false,{"key":16,"text":17,"correct":18},"B","⑤→②→①→④→③",true,{"key":20,"text":21,"correct":14},"C","②→⑤→④→①→③",{"key":23,"text":24,"correct":14},"D","⑤→③→①→④→②","",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]