[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134735":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134735,796,1,"单选题","（2019年真题）关于预应力钢筋混凝土拆模说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人应在拟定拆模时间的12h以前，并应取得监理工程师同意",false,{"key":16,"text":17,"correct":14},"B","非承重侧模板应在混凝土强度，设计未规定达到2.5MPa时方可拆除侧模板",{"key":19,"text":20,"correct":14},"C","钢筋混凝土结构的承重模板、支架，应在混凝土强度能承受其自重荷载及其他可能的叠加荷载时，方可拆除",{"key":22,"text":23,"correct":24},"D","预应力混凝土结构，其侧模、底模及支架应在结构建立预应力后方可拆除",true,"P129-134 本题考查的是模板、支架和拱架的拆除。对预应力混凝土结构，其侧模应在预应力钢束张拉前拆除；底模及支架应在结构建立预应力后方可拆除，故选项D错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]