[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134725,796,1,"单选题","预应力张拉的千斤顶与压力表，不需要重新标定的情形是（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","使用时间达到3个月",true,{"key":16,"text":17,"correct":18},"B","张拉次数超过300次",false,{"key":20,"text":21,"correct":18},"C","千斤顶检修后",{"key":23,"text":24,"correct":18},"D","更换新压力表","本题考查的是预应力混凝土工程施工。当处于下列情况之一时，应重新进行标定：（1）使用时间超过6个月；（2）张拉次数超过300次；（3）使用过程中千斤顶或压力表出现异常情况；（4）千斤顶检修或更换配件后。参见教材。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]