[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134710,796,1,"单选题","（2020年真题）热拌沥青混凝土路面施工工艺包括：①路缘石安装②试验段施工③喷洒透层油④混合料压实⑤沥青混合料摊铺⑥路面成型监测，其施工顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②→③→①→⑥→⑤→④",false,{"key":16,"text":17,"correct":18},"B","①→③→②→⑤→④→⑥",true,{"key":20,"text":21,"correct":14},"C","②→①→③→⑤→④→⑥",{"key":23,"text":24,"correct":14},"D","①→②→③→⑥→⑤→④","P84-87",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]