[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134702,796,1,"单选题","关于级配碎石基层施工的说法，正确的是（ ）。2013年",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","碎石颗粒组成的级配曲线应为直线",false,{"key":16,"text":17,"correct":18},"B","级配碎石应在最佳含水量时进行碾压",true,{"key":20,"text":21,"correct":14},"C","应使用12t 以上的三轮压路机碾压，不得采用振动压路机碾压",{"key":23,"text":24,"correct":14},"D","级配碎石基层碾压完成后即可开放交通","碎石颗粒组成的级配曲线应为圆滑曲线；级配碎石应在最佳含水量时进行碾压；应使用18—21t 的三轮压路机碾压，采用振动压路机碾压；级配碎石、级配砾石基层未做透层沥青或铺筑封层钱，严禁开放交通。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]