[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134691,796,1,"单选题","沥青贯入式路面的施工工序代号如下：①撒布主层集料；②浇洒第一层沥青；③采用6～8t 钢轮压路机碾压；④撒布第一层嵌缝料；⑤采用8～12t 钢轮压路机碾压。上述5 道工序正确的施工顺序是（ ）。2012年",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","②一①一④一③一⑤",false,{"key":16,"text":17,"correct":14},"B","②一①一③一④一⑤",{"key":19,"text":20,"correct":21},"C","①一③一②一④一⑤",true,{"key":23,"text":24,"correct":14},"D","①一⑤一②一④一③","路面沥青稳定基层（底基层）施工。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]