[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134684,796,1,"单选题","（2020年真题）软土地区路堤施工期间，坡脚水平位移速率24h应不大于（ ）mm。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","10","P18-34 施工期间，路堤中心线地面沉降速率24h应不大于10~15mm ，坡脚水平位移速率24h应不大于5mm。应结合沉降和位移观测结果综合分析地基稳定性。填筑速率应以水平位移控制为主，超过标准应立即停止填筑。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]