[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134678,796,1,"单选题","柱板式锚杆挡土墙墙后的土压力传递顺序，正确的是（ ）。2013年",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","墙后的土压力→锚杆→挡土板",false,{"key":16,"text":17,"correct":14},"B","墙后的土压力→挡土板→锚杆",{"key":19,"text":20,"correct":21},"C","墙后的土压力→挡土板→肋柱→锚杆",true,{"key":23,"text":24,"correct":14},"D","墙后的土压力→肋柱→挡土板→锚杆","柱板式锚杆挡土墙是由挡土板、肋柱和锚杆组成，肋柱是挡土板的支座，锚杼是肋柱的支座，墙后的侧向土压力作用于挡土板上，并通过挡土板传给肋柱，再由肋柱传给锚杆；壁板式锚杆挡土墙是由墙面板（壁面板）和锚杆组成，墙面板直接与锚杆连接，并以锚杆为支撑，土压力通过墙面板传给锚杆。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]