[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134664,796,1,"单选题","砂井套管法施工工艺中，拔管的紧前工序是（）。2016年",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","加料压实",true,{"key":16,"text":17,"correct":18},"B","桩管沉入",false,{"key":20,"text":21,"correct":18},"C","插入套管",{"key":23,"text":24,"correct":18},"D","机具移位","将带有活瓣管尖或套有混凝土端靴的套管沉到预定深度，然后在管内灌砂后，拔出套管，形成砂井。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]