[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134654,796,1,"单选题","（2019年真题）关于预制梁场布设错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","结合梁板的尺寸、数量、架设要求以及运输条件等情况进行综合选址",false,{"key":16,"text":17,"correct":18},"B","监理指定预制场位置",true,{"key":20,"text":21,"correct":14},"C","周围无塌方、滑坡、落石、泥石流、洪涝等地质灾害",{"key":23,"text":24,"correct":14},"D","场地建设前施工单位应将梁场布置方案报监理工程师审批","P412-416 本题考查的是预制场布设。预制场位置由施工单位结合梁板的尺寸、数量、架设要求以及运输条件等情况进行综合选址，并不是由监理指定预制场位置，故选项B错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]