[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134651,796,1,"单选题","关于控制供料成本措施的说法，错误的是（ ）。2016年",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制施工现场运输损耗",true,{"key":16,"text":17,"correct":18},"B","控制采购及保管费",false,{"key":20,"text":21,"correct":18},"C","控制实际采购价低于预算中的材料原价",{"key":23,"text":24,"correct":18},"D","控制实际发生的运杂费低于预算运杂费","控制供料成本的措施：（1）购入原价的核算：即以预算中的材料原价与实际采购价格的比较节超；（2）运杂费的核算：是以实际发生的运杂费与预算运杂费比较节超；（3）场外运输损耗的核算：根据概预算编制办法，部分地材和水泥、沥青等有场外运输定额损耗；（4）采购及保管费的核算：材料的采购及保管费包括采购费、仓管费、仓储损耗和物资人员的开支四个部分。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]