[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134648,796,1,"单选题","项目部编制材料供应计划时，主要依据是（ ）。2013年",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","材料用款计划",false,{"key":16,"text":17,"correct":18},"B","材料需用量计划",true,{"key":20,"text":21,"correct":14},"C","材料采购计划",{"key":23,"text":24,"correct":14},"D","材料价格调整计划","材料供应计划是企业物资部门根据材料需要计划而编制的计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]