[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134643,796,1,"单选题","投标报价计算时，所填入的工程量清单的单价包括人工费、材料费、机械使用费，其他工程费、间接费、利润和税金以及风险金等全部费用，构成基础单价，此种方法称（ ）。2016年",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工料单价法",false,{"key":16,"text":17,"correct":14},"B","基价计量法",{"key":19,"text":20,"correct":21},"C","综合单价法",true,{"key":23,"text":24,"correct":14},"D","清单计价法","综合单价计算方法。按综合单价计算报价是所填入工程量清单的单价，应包括人工费、材料费、机械使用费、其他工程费、间接费、利润和税金以及风险金等全部费用，构成基础单价，即综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]