[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134641,796,1,"单选题","（2019年真题）合同约定共同延误按不利于承包商原则，由于恶劣环境和业主延迟发放图纸共同存在，承包商可以索赔（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期补偿和经济补偿",false,{"key":16,"text":17,"correct":18},"B","工期补偿，不可以经济补偿",true,{"key":20,"text":21,"correct":14},"C","工期不可补偿，经济可以补偿",{"key":23,"text":24,"correct":14},"D","工期和经济都不可补偿","P372-376 本题考查的是公路项目施工索赔管理。不利于承包商原则是指在交叉时段内，只要出现了承包商的责任或风险，不管其出现次序，亦不论干扰事件的性质，该时段的责任全部由承包商承担。所以当不可补偿延误与可补偿延误同时存在时，承包人可获得工期延长，但不能要求经济补偿。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]