[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134639":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134639,796,1,"单选题","关于分包合同管理关系的说法，错误的是（ ）。2017真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人与分包人没有合同关系",false,{"key":16,"text":17,"correct":14},"B","监理人对分包人的现场施工不承担协调和管理义务",{"key":19,"text":20,"correct":21},"C","监理人就分包工程施工发布的指示均应发给承包人和分包人",true,{"key":23,"text":24,"correct":14},"D","承包人对分包工程的实施具有全面管理责任","本题考查的是公路工程分包合同管理。选项C，监理人就分包工程施工发布的任何指示均应发给承包人。参见教材。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]