[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134638,796,1,"单选题","根据《公路工程标准施工招标文件》（2009 年版），组成合同的各项文件包括：①中标通知书；②合同协议书及各种合同附件；③项目专用合同条款；④已标价工程量清单等。除项目合同条款约定外，合同文件的优先解释顺序是（ ）。2012年",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①一②一③一④",false,{"key":16,"text":17,"correct":14},"B","③一①一②一④",{"key":19,"text":20,"correct":14},"C","②一③一④一①",{"key":22,"text":23,"correct":24},"D","②一①一③一④",true,"解释合同文件的优先顺序：1.合同协议书及各种合同附件（含评标期间和合同谈判过程中的澄清文件和补充资料）。2.中标通知书。3.投标函及投标函附录。4.项目专用合同条款。5.公路工程专用合同条款。6.通用合同条成。7.技术规范。8.图纸。9.已标价工程量清单。10.承包人有关人员、设备投入的承诺及投标文件中的施工组织设计。11.其他合同文件。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]