[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134629":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134629,796,1,"单选题","关于悬臂浇筑法施工安全控制的说法，错误的是（ ）。2013年",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","挂篮组拼后，要进行全面检查，并做动载试验",true,{"key":16,"text":17,"correct":18},"B","挂篮上的施工遇6 级以上大风应停止作业",false,{"key":20,"text":21,"correct":18},"C","挂篮作业平台边缘必须设场脚板",{"key":23,"text":24,"correct":18},"D","已浇筑过的梁段上应安装1.2m 高的桥面临时护栏","挂篮组拼后，要进行全面检查，并做静载试验。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]