[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134619,796,1,"单选题","根据《公路工程标准施工招标文件》（2009版），工程量清单计日工明细表中所列工程数量为（ ）。2017真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标方估计的工程量",true,{"key":16,"text":17,"correct":18},"B","招标设计图纸所列工程量",false,{"key":20,"text":21,"correct":18},"C","投标方估计的工程量",{"key":23,"text":24,"correct":18},"D","实际完成工程量","本题考查的是编写工程量清单注意事项。计日工清单是用来处理一些附加的或小型的变更工程计价的，清单中计日工的数量完全是由业主虚拟的，用以避免承包人在投标时计日工的单价报得太离谱，有了计日工清单会使合同管理很方便。参见教材。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]