[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134616,796,1,"单选题","（2020年真题）适用于时标网络图的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图",false,{"key":16,"text":17,"correct":14},"B","S形曲线",{"key":19,"text":20,"correct":14},"C","香蕉图",{"key":22,"text":23,"correct":24},"D","前锋线比较法",true,"P303-307 前锋线比较法是通过绘制某检查时刻工程项目实际进度前锋线，进行工程实际进度与计划进度比较的方法，它主要适用于时标网络计划。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]