[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134615":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134615,796,1,"单选题","（2019年真题）施工进度计划检查不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量完成情况",false,{"key":16,"text":17,"correct":14},"B","资源使用及进度的互配情况",{"key":19,"text":20,"correct":14},"C","上次检查提出问题的处理情况",{"key":22,"text":23,"correct":24},"D","标准化执行情况",true,"P303-307 本题考查的是公路工程进度控制管理。 公路工程项目进度检查应包括下列内容： （1）工作量的完成情况； （2）工作时间的执行情况； （3）资源使用及进度的互配情况； （4）上次检查提出问题的处理情况。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]