[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134585,796,1,"单选题","以下设计变更不属于较大设计变更范畴的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超过施工图设计批准预算",false,{"key":16,"text":17,"correct":18},"B","收费方式及站点位置、规模发生变化",true,{"key":20,"text":21,"correct":14},"C","单项工程费用变化超过500万元的变更",{"key":23,"text":24,"correct":14},"D","隧道的数量或方案发生变化","2020版教材P449\u002F2019版教材P439 有下列情形之一的属于较大设计变更：连续长度2krn以上的路线方案调整的；连接线的标准和规模发生变化的；特殊不良地质路段处置方案发生变化的；路面结构类型、宽度和厚度发生变化的；大中桥的数量或结构形式发生变化的；隧道的数量或方案发生变化的；互通式立交的位置或方案发生变化的；分离式立交的数量发生变化的；监控、通信系统总体方案发生变化的；管理、养护和服务设施的数量和规模发生变化的；其他单项工程费用变化超过500万元的；超过施工图设计批准预算的。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]