[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134557":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134557,796,1,"单选题","连续刚构桥悬臂拼装施工的主要工艺顺序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","块件预制→预应力张拉→移运→整修→施工接缝处理→吊装定位",false,{"key":16,"text":17,"correct":18},"B","块件预制→移运→整修→吊装定位→预应力张拉→施工接缝处理",true,{"key":20,"text":21,"correct":14},"C","块件预制→预应力张拉→施工接缝处理→移运→整修→吊装定位",{"key":23,"text":24,"correct":14},"D","块件预制→移运→整修→预应力张拉→吊装定位→施工接缝处理","2020版教材P203\u002F2019版教材P197 悬臂拼装主要工序的主要工序包括：块件预制、移运、整修、吊装定位、预应力张拉、施工接缝处理等，各道工序均有其不同的要求，并对整个拼装质量具有密切影响。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]