[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134553,796,1,"单选题","大跨径劲性骨架混凝土拱桥拱圈浇筑前应进行（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工观测",false,{"key":16,"text":17,"correct":18},"B","加载程序设计",true,{"key":20,"text":21,"correct":14},"C","施工组织设计",{"key":23,"text":24,"correct":14},"D","方案调整","2020版教材P204\u002F2019版教材P199198 大跨径劲性拱圈混凝土拱圈（拱肋）的浇筑，可采用分环多工作面均衡浇筑法、水箱压载分环浇筑法和斜拉扣挂分环连接浇筑法。浇筑前应进行加载程序设计，正确计算和分析钢骨架以及钢骨架与先期混凝土层联合结构的变形、应力和稳定安全度，并在施工过程中进行监控。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]