[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134546,796,1,"单选题","先张法预应力筋的张拉过程中，张拉操作时，应对断丝情况进行检查，其要求（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同一构件内预应力钢丝、钢绞线的断丝数量不得超过1%，同时对于预应力钢筋不允许断筋",true,{"key":16,"text":17,"correct":18},"B","同一构件内预应力钢丝的断丝数量可不超过2根，且不得超过1%，同时对于预应力钢筋不允许断筋",false,{"key":20,"text":21,"correct":18},"C","同一构件内预应力钢丝、钢绞线不允许断丝，同时对于预应力钢筋断丝数量不得超过1%",{"key":23,"text":24,"correct":18},"D","同一构件内预应力钢丝、钢绞线的断丝数量不得超过1%，同时对于预应力钢筋不得超过1根","2020版教材P147\u002F2019版教材P166 张拉时，同一构件内预应力钢丝、钢绞线的断丝数量不得超过1%同时对于预应力钢筋不允许断筋。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]