[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134540,796,1,"单选题","在浇筑箱梁截面混凝土时，若设计无明确要求，一般的浇筑顺序包括：①浇筑混凝土时，必须从悬臂端开始，两个悬臂端应对称均衡地进行浇筑；②在浇筑混凝土的同时应注意对预应力管道的保护，浇筑后应及时对管道清孔，以利穿束；③浇筑混凝土时，应加强振捣，对于高箱梁混凝土施工，可采用内侧模开仓振捣；下述关于其顺序正确的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①→②→③",false,{"key":16,"text":17,"correct":14},"B","③→①→②",{"key":19,"text":20,"correct":14},"C","②→①→③",{"key":22,"text":23,"correct":24},"D","①→③→②",true,"2020版教材P186\u002F2019版教材P180 1、浇筑混凝土时，必须从悬臂端开始，两个悬臂端应对称均衡地进行浇筑。2、浇筑混凝土时，应加强振捣，对于高箱梁混凝土施工，可采用内侧模开仓振捣。3、在浇筑混凝土的同时应注意对预应力管道的保护，浇筑后应及时对管道清孔，以利穿束。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]