[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134538":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134538,796,1,"单选题","桥梁上部结构转体施工工艺包括脱架、撤锚合龙、转动、转盘封固，正确的工艺顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","转盘封固→转动→脱架→撤锚合龙",false,{"key":16,"text":17,"correct":14},"B","转动→转盘封固→撤锚合龙→脱架",{"key":19,"text":20,"correct":14},"C","转盘封固→转动→撤锚合龙→脱架",{"key":22,"text":23,"correct":24},"D","脱架→转动→转盘封固→撤锚合龙",true,"2020版教材P193\u002F2019版教材P187 转体施工工艺包括：脱架→转动→转盘封固→撤锚合龙。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]