[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1134536,796,1,"单选题","关于缆索吊装施工的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主索系统试吊分静载试吊和吊重运行两步",true,{"key":16,"text":17,"correct":18},"B","试吊重物可以为构件、钢筋混凝土预制件",false,{"key":20,"text":21,"correct":18},"C","风缆应成对称布置",{"key":23,"text":24,"correct":18},"D","地锚应预先试拉","2020版教材P196\u002F2019版教材P190 主缆宜采用钢丝绳，安全系数应不小于3。主索系统试吊分跑车空载反复运转、静载试吊和吊重运行三步。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]