[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134528,796,1,"单选题","下列关于边坡失稳的预防及处理措施错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基坑开挖之前，应先做好地面排水系统",false,{"key":16,"text":17,"correct":18},"B","基坑开挖时应抓紧时间进行开挖，开挖时间不能过长，并且要开挖结束后及时支护",true,{"key":20,"text":21,"correct":14},"C","基坑应尽量安排在少雨季节施工",{"key":23,"text":24,"correct":14},"D","坑顶边缘应有一定的距离作护道，堆载距坑缘不小于1m","2020版教材P154\u002F2019版教材P145 1.基坑开挖之前，应先做好地面排水系统，在基坑顶外缘四周应向外设置排水坡或设置防水梁，并在适当距离设截水沟，且应防止水沟渗水，避免影响坑壁稳定。2.坑顶边缘应有一定的距离作护道，堆载距坑缘不小于0.5m，动载（包括机械及机械通道）距坑缘不小于1.0m，垂直坑壁坑缘边的护道还应适当增宽，堆置弃土的高度不得超过1.5 m。3.挖基经过不同土层时，边坡可分层而异，视情况留平台。4.在施工过程中注意观察坑缘顶面有无裂缝，坑壁有无松散塌落现象。5.对地质情况发生变化的地层应及时增设支护；水文地质条件欠佳时应提前采取加固措施。6.基坑自开挖起，应抓紧连续不断施工直至基础完成，施工时间绝不可延续太长。7.严格按规范、图纸施工。8.基坑应尽量安排在少雨季节施工。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]