[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134525":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134525,796,1,"单选题","钻孔灌注桩施工的主要工序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻孔→埋设护筒→制备泥浆→清底→钢筋笼制作与吊装→灌注水下混凝土",false,{"key":16,"text":17,"correct":18},"B","埋设护筒→制备泥浆→钻孔→清底→钢筋笼制作与吊装→灌注水下混凝土",true,{"key":20,"text":21,"correct":14},"C","钻孔→灌注水下混凝土→埋设护筒→制备泥浆→钻孔→清底→钢筋笼制作与吊装",{"key":23,"text":24,"correct":14},"D","制备泥浆→埋设护筒→钻孔→钢筋笼制作与吊装→清底→灌注水下混凝土","2020版教材P156\u002F2019版教材P147 钻孔灌注桩施工的主要工序有：埋设护筒、制备泥浆、钻孔、清底、钢筋笼制作与吊装以及灌注水下混凝土等",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]