[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1134264,796,1,"单选题","中央分隔带施工中埋设横向塑料排水管的进口用土工布包裹的作用是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","增大强度",false,{"key":16,"text":17,"correct":14},"B","增大透水性",{"key":19,"text":20,"correct":14},"C","防止漏水",{"key":22,"text":23,"correct":24},"D","防止碎石堵塞",true,"2020版教材P107\u002F2019版教材P103 4.埋设塑料排水管。埋设要求：一端应插入中央分隔带范围内的纵向排水盲沟位置，另一端应伸出路基边坡外。横向塑料排水管的进口须用土工布包裹，防止碎石堵塞。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]