[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134166":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1134166,796,1,"单选题","柱板式锚杆挡土墙墙后的土压力传递顺序，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","墙后的土压力→锚杆→挡土板",false,{"key":16,"text":17,"correct":14},"B","墙后的土压力→挡土板→锚杆",{"key":19,"text":20,"correct":21},"C","墙后的土压力→挡土板→肋柱→锚杆",true,{"key":23,"text":24,"correct":14},"D","墙后的土压力→肋柱→挡土板→锚杆","2020版教材P39\u002F2019版教材P36 柱板式锚杆挡土墙是由挡土板、肋柱和锚杆组成，肋柱是挡土板的支座，锚杆是肋柱的支座，墙后的侧向土压力作用于挡土板上，并通过挡土板传给肋柱，再由肋柱传给锚杆，由锚杆与周围地层之间的锚固力，即锚杆抗拔力使之平衡，以维持墙身及墙后土体的稳定。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]