[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1134153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1134153,796,1,"单选题","先沿路堑纵向挖掘一条通道，然后将通道向两侧拓宽以扩大工作面，并利用该通道作为运土路线及场内排水的出路；该层通道拓宽至路堑边坡后，再挖下层通道，如此向纵深开挖至路基标高。上述作业方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分层纵挖法",false,{"key":16,"text":17,"correct":18},"B","通道纵挖法",true,{"key":20,"text":21,"correct":14},"C","分段纵挖法",{"key":23,"text":24,"correct":14},"D","多层横向全宽挖掘法","2020 \u002F 2019版教材P3 此题考查土质路堑施工技术。作业方法包括横向挖掘法、纵向挖掘法和混合式挖掘法三类：1.横向挖掘法（1）单层横向全宽挖掘法：从开挖路堑的一端或两端按断面全宽一次性挖到设计标高，逐渐向纵深挖掘，挖出的土方一般都向两侧运送。该方法适用于挖掘浅且短的路堑。（2）多层横向全宽挖掘法：从开挖路堑的一端或两端按断面分层挖到设计标高，适用于挖掘深且短的路堑。2.纵向挖掘法土质路堑纵向挖掘多采用机械作业，具体方法有：（1）分层纵挖法：沿路堑全宽，以深度不大的纵向分层进行挖掘，适用于较长的路堑开挖。（2）通道纵挖法：先沿路堑纵向挖掘一通道，然后将通道向两侧拓宽以扩大工作面，并利用该通道作为运土路线及场内排水的出路。该层通道拓宽至路堑边坡后，再挖下层通道，如此向纵深开挖至路基标高，该法适用于较长、较深、两端地面纵坡较小的路堑开挖。（3）分段纵挖法：沿路堑纵向选择一个或几个适宜处，将较薄一侧堑壁横向挖穿，使路堑分成两段或数段，各段再纵向开挖。该法适用于过长、弃土运距过远、一侧堑壁较薄的傍山路堑开挖。3.混合式挖掘法多层横向全宽挖掘法和通道纵挖法混合使用。先沿路线纵向挖通道，然后沿横向坡面挖掘，以增加开挖面。该法适用于路线纵向长度和挖深都很大的路堑开挖。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]